We have decided that our "basement" should no longer be called
that - after all it is was never really below ground, and now it is
not dark, damp or dingy. So, we are going with "Garden Level"
or the "Ground Floor" as the next floor up is still the Main
Floor of the house. Whatever we call it, we have a lot of work ahead
to turn it into something useful...

Saturday January 7th, 2006
Well, that was how it looked back in August, when the
new floor had just been poured. Unfortunately, now being the middle
of a very, very wet winter, by the time we started working in here the
ground floor looked more like this, as storing construction materials
outside was just out of the question!

So, the aim is not to have to move the piles of materials
more times than essential!
Anyway, at long last (after months of cold outdoor work) it's finally
time to get to work on the sub-floor...

Sunday February 5th
After a couple of weekends doing more fun things (skiing,
hosting visitors), we are finally on a roll (having moved all the materials
for the last time!) and things are coming along quickly on the subfloor

Sunday February 26th
A few more weekends at it, and the subfloor is finished!

Then March and April passed us by completely, with Glenn
too busy
with work during March, and both of us off on vacation in April...
Sunday May 28th
A few weekends of reworking some of our heating and
cold air ducting lets us optimize our drop-ceiling profile in the basement.
Meanwhile, Glenn has become a sheet metal pro, has taken out the walls
from our old chimney, framed the extension to our main floor bathroom,
rerouted the hot air trunk to the attic, and moved heat and cold air
utilities out of walls on the main floor we want to demolish later...
Sometimes finishing the ground floor can have some unexpected side detours
along the way!
|
It's a little hard to tell what is what in this photo, as the
shiny new heating trunk (behind the second stud) is reflecting
the door frame and wall colour, and in the corner behind the
wall frame, we have put in some cheap ply panel to cover the
dirty old framing from inside the chimney. The floor and ceiling
panels help you to see where the chimney used to be...
|
Saturday June 17th
Finally finished on the duct work, and on to framing,
with the new bathroom starting to take shape...

Saturday July 8th
With a few more weekends work, framing of the bathroom
(right) and bedroom (with closet) are completed, and the central vacuum
has been extended for an outlet on this floor...

Sunday July 16th
In the back corner, with some framing, insulation and
a little bit of drywall in place, we're set to start building our new
stairs down from the main floor!

Saturday July 22nd
With two days off work during the week, by Saturday
lunchtime the stairs are done! (At least for now - we will be putting
in proper oak treads and risers later, when everything else is finished...)


Sunday September 10
Well, August sped by, as we finished up minor framing
details, and did a bunch of retrofit work on the electrical to separate
existing wiring for upstairs that needed stay, from wiring on the ground
floor that needed to be ripped out. Then we had to go out and find and
buy all our lights. Finally, it is time to start all the new electrical
wiring...

Saturday September 16
Here is how to mock up a bed in the new bedroom, to
help visualize where to install the lights...

Sunday October 22
Still working on wiring! Trust us, we are going to have
no shortage of light, sound, phone, video and data in this house...

Meanwhile, Mum & Dad are here visiting from Melbourne
and are keen to help out. So they were able to make a good start on
the insulation for us...


Sunday November 4
Details, details, details! To completely wrap up all
the different parts of the process that have to be finished before the
vapour barrier and drywall go in, it is amazing the number of fiddly
little details that have to be dealt with - especially when you are
preparing for future upstairs renovations before closing in the ceilings
downstairs! November and December ended up being a painful drag of finishing
up details - things that had been left on the "to do" list
as they didn't need to be done right away, but now just had to be done...

Saturday December 16
While Glenn was working the technical details, Theresa
was able to finish all of the insulating, right down to pipe insulation
on our hot water pipes...

Monday December 18
Working overtime (not Saturday or Sunday) to try to
make some progress, Glenn is wrapping the floor up with nice red tape
for Christmas! No, not just for fun - a required part of the vapour
barrier system...

Sunday January 14, 2007
This is a big weekend for us, having gotten sign-offs
from the City building and plumbing inspectors during the week that
we are "OK to cover" everything, and can start to drywall.
The bathroom is first up, with Theresa cutting out the opening for our
recessed medicine cabinet...

Meanwhile, on the inside of the room, things are coming
along well...

Saturday & Sunday January 20 & 21
Our bathroom cabinets are ready early, and waiting in
a friend's storeroom to be installed. So, we had someone come in to
tape and finish the bathroom drywall during the week, and suddenly we
are on to painting...

Saturday February 10
So, we got everything done in time for the cabinet installer
to come and install our bathroom cabinets. (The countertop will come
later.)

We have also been able to install our "art"
glass window in the bathroom, to give some natural light to this interior
room. It really is great to see things coming together at long last!

After a weekend off to relax and ski at Whistler, we
are now into the second weekend of hanging drywall for the rest of the
ground floor. The ceilings are just about done, with huge help from
renting a lifter to help get the 75 lb panels up and overhead safely...

And here is a solution to laying a level ceiling on
the underside of a sloped porch...

Sunday February 18
With the ceilings done, it is time to get started hanging
the walls - starting with our new bedroom closet...

Sunday March 4
After 2 more weekends of work, things are really moving
along, and the walls are all in on our new rec. room and front door...


Tuesday May 29
Yes, that's right, suddenly 2.5 months have passed with
virtually no progress at all! In March, Glenn was working crazy hours
at the office. In April, we were away in Cuba and Mexico for a very
well-needed rest, then a few more crazy weeks at work for Glenn once
we got back...
But back in early March, we had managed to get the tile-setter
in to do the bathroom tile work. After that suddenly it is the end of
May before we finally have the time to do the last couple of hours work
required after tiling but before having the plumber back to finish the
bathroom installation, before we can put up the last four sheets of
drywall, before we can have someone come in and mud and tape the drywall
for us!!! Anyway, eventually we got back on track, and the bathroom
installation was finished (after which it became the new place to store
all our supplies). We still have to install the shower curtain rail,
which is parked in our dining room...

Saturday June 2
Hardly a flattering photo, but Glenn manages to get
the electrical finished and the motor installed to get our new jet tub
working!!! Woo-hoo!!!

Then the last drywall sheets went up outside the bathroom...

And finally we were ready for someone to come to tape
and mud for us...

Of course, it took a couple of weeks to find someone
available, and then the work was actually done while we were in New
Orleans, so no "in progress" photos of the drywall guys. But
when we got back, it was all done and smooth (and dusty)...

Monday July 1 - Canada Day

After a couple of days to clean up, it was finally time
to get painting!!

Even just getting the primer on is enough to make things
start to look somewhat finished...

(No, that's not colour on the wall yet, just different
light colour.)
Sunday July 15
Suddenly we are rocking along again at great speed,
enthused by seeing the light at the end of the tunnel (and the colours
on the walls)! With Theresa painting some weekdays, and up both working
on things in the evenings, two weeks later the laundry is done, complete
with working lights, power, and new appliances that had been sitting
in our garage for six months...

Plus, the bedroom is almost finished in terms of painting,
and Glenn is working on the lighting there...

Plus, the ceilings are painted in the rec. room, and
Theresa is getting a good start on the walls there...

With one coat finished by the end of the day...

Wow, after months of snail-like progress, it is great
to be moving along so fast!!
BC Day Long Weekend: August 4-6th
With all the walls painted, it is time to start on the
floors. The bedroom is the first room to get the finishing treatment.
Flooring is a slow process to get started, and by Sunday night Glenn
was happy just to have all the guide lines squared off between the different
rooms on this floor, and to have the first half dozen rows of flooring
down in the bedroom...


But, by Monday evening, the bedroom floor is finished,
and looking great!

And just in time, because the next day, installers were
coming to put in our bedroom closet...

Tuesday September 4th
Unfortunately, our brand new floor suffered some damage
at the hands of the closet installer, which is one reason we prefer
to do things ourselves rather than deal with the stress of tradespeople.
But the closet company was good about it, and we hired a hardwood company
to come in and replace the damaged area. But that slowed things down
once again.
For Labour Day, we made it an extended long weekend,
as we are really down to the very short strokes on the bedroom. We feel
like we are going around in ever decreasing circles, filling nail holes
and patching and painting the few dings our wall have suffered since
they were painted.
Over the weekend, we have completed the last area of
flooring in the bedroom, and extended the floor to the bathroom and
out into the rec. room to give us "seam free" floor throughout...

...installed our oak ledges in the bedroom, the second
external window frame, the last of our bedroom lighting, and most of
the baseboards...

...and installed both doors for the bedroom...

We have a few pieces of trim left to do during the evenings
this week, and then next weekend we are moving downstairs - at long
last!!!
Sunday September 9th
Well, it was a really big day for us today! After a
busy weekend painting doors and touching up nail holes in the trim,
by late afternoon Sunday, our bedroom was finished enough that we actually
moved in!!! Three years after drawing up our plans for the ground floor,
and probably about five years after first talking about raising the
house, we finally have a beautiful new bedroom!!!

Summer 2008
And to wrap things up, here is a shot of the great security
bars we had made for the front window on our bedroom...
